  • HPH242 : How to make a cohousing scheme a reality – with Phil McGeevor from Cannock Mill Cohousing

    HPH242 : How to make a cohousing scheme a reality – with Phil McGeevor from Cannock Mill Cohousing

    Phil McGeevor, Chair of Cannock Mill Cohousing, describes the 12-year journey it’s taken to realise their cohousing community for older adults.

    Interview with Phil McGeevor

    In 2007, a small group who used to go on holiday together, discussed the idea of developing a cohousing scheme together. Phil McGeevor and his wife were amongst the first wave of people to join.

     

    Although Phil was unfamiliar with the concept, he soon became very enthusiastic and keen to take it forward.

    “I loved the idea of being able to build not just a house but a community. I liked the design ideas of our architect and we agreed right from the start it would be to Passivhaus standards, if that was at all possible.

    I liked some of the eco aspects of being able to share, not having twenty-three lawnmowers and the rest. It seemed a very sensible thing. And I liked the combination of the privacy of your own house but the connection to the common house, the mill in our case, and to your neighbours. And through making decisions together, I thought that was just a good way to live. “

    The scheme has largely been self financed

    This has mostly been through a variety of pensions and savings within the group, with the ability to use a developer’s loan of up to £4.5 million from Homes England. This was the first cohousing group they had helped, with a loan that is designed for developers to be able to buy a plot of land that might otherwise be uneconomical and not able to raise private finance on.

    There was a broad search area for a site

    Finding any suitable building plot can be a drawn out affair, but with cohousing it invariably takes considerably longer. The biggest challenge is usually in trying to compete with more conventional developers, so often the options that remain tend to be more challenging sites.

    What worked in their favour was having a good skill-set among the group, with Anne Thorne providing experience as their architect. And with many members of the group looking towards retirement and being flexible about location, they had a broad geographic search area encompassing everywhere that was within 90 minutes from London.

    It was 8 years before they bid on a plot

    Choosing the site was a balance of the factual side of things, such as the size, constraints, planning permissions, price and what could be built there, together with the emotional aspect of how they felt about it. Viewing the site on a wet and muddy day in November, they were still able to visualise how it could be beautiful.

    While they had spent some money carrying out due diligence on other plots, this was the first they had bid on. Taking a year to make the purchase, it had been around 9 years to get to the stage of owning their plot of land.

    In committing to the site in Colchester, Essex, and having to part with large sums of money, they invariably had a few members drop out at this stage, but still had enough to take it forward.

     

    The group demographic impacted on design

    At just over two acres, the focal point of the site is a 15th Century, three storey Victorian mill, with mill pond behind.

    The flats are connected to The Mill and follow an L shape around the pond. There are a further three blocks of terrace housing that also follow the line around the pond.

    Key to the design was making sure the units would be energy efficient and beautiful to live in.

    They have six one-and two-bedroom flats, a series of two-bedroom houses and some three-bedroom houses. Phil says that in retrospect, for the group’s demographic, that two-bedroom units would probably be ideal.

    They are built on piled foundations, with timber frames and a rendered exterior. They have living green roofs and face across the mill pond to The Mill itself.

    There are balconies at the rear which, because of the slope of the site, are on a similar level with the shared gardens. There is also a walkway between the balconies which adds to the sense of community.

    Extensive groundworks increased costs

    They used a tender process to select their contractor, carrying out due diligence on them before making their decision. Although they hadn’t built Passivhaus houses before, they had completed a Passivhaus school and seemed to have strengths that the other bidders didn’t have.

    The first contract they signed with them was for the groundworks. With water being a feature of the site, there was a serious amount of engineering in the background, behind the attractive aesthetic!

    “You have to find compromises. It’s been an absolute lesson in life”

    A member of the group spent time visiting and staying at many other cohousing schemes, to learn from them and advise the group as to what worked well and what they had difficulties with.

    “Every group thinks it’s invented the wheel and the right way of doing it, but you can pick and mix from the different groups, what you like and what you think will work for you. Because every group is slightly different. “

    Although the members formed different committee groups, such as for finding the land, overseeing the building work etc, the different groups would come together as an executive and decisions made as a whole.

    Phil explains that very rarely have they had to resort to voting to make a decision. Generally they are able to work through issues until they reach a consensus.

    “So, the trust in the group is essential and it’s something you do everything you can to preserve and develop because you know it’s going to be really important for the long-term success of how you live there. And I’m just amazed that a group of people who mostly didn’t know each other until they got involved with this, can develop such a high-level trust. And of course, it’s an incredibly efficient mechanism, trust, compared to trying to tie each other up in contracts or red tape. And it’s worked very well for us.”

    As time has gone on they’ve found that making decisions together has become easier. Often it’s because they know more about the expertise of the individual group members and who they should be listening to on which subjects.

    Groups have different responsibilities

    Originally many of the members of the group were from the London area but now the site has been purchased some have sold their properties and are renting closer by. They have also had new members join from the local area.

    Early on they would hold meetings in London but as the project has progressed they have moved to The Mill on the site, village halls, or wherever the particular group that is meeting chooses is convenient.

    Group committees have included building, finance, legal, communications and membership.

    As the project moved forward they had to establish a new series of groups to cover different aspects of living in The Mill. So now there is a gardening group, and also a group for each floor of The Mill, including a kitchen and utilities room group who look at the equipment they need to buy, cost it up and present it back to the board.

    Be realistic about finances

    With moving in just a few months away, Phil is conscious of just how much work still needs to be done.

    “I want us to be in there. I want that to be well-planned and go as smoothly as it can. I know there will be difficulties and obstacles to get through. But I’m confident from our past experience of how we’ve tackled those, that we will get through them.”

    Phil is keen to point out to any other cohousing groups that are planning their own scheme, to be realistic about the finances.

    “I think I would be rather robust in telling them that a tooth fairy isn’t going to come down and do it for them. Nobody is going to say, ‘I’d love to finance this for you, and it will be terribly cheap for you and it will all be wonderful.’
    You have control of it yourself, but you have to do it. You have to raise that money. It is a pretty hard-headed commercial thing, in the end. It wouldn’t get built otherwise. A contractor is going to look very seriously at you to see that you have the means to do it, certainly the finance, but also the skills. You need to get those things lined up.”

     

    Regen Media

    Here at Regen Media we produce videos for the construction industry, and ideally ecological construction. So if there’s a project you think we might be able to help on, do please get in touch. 

     

    Find out more

    Visit the website of Cannock Mill Cohousing

    Follow Cannock Mill Cohousing on Twitter

    Find out more about Anne Thorne Architects

     

    Transcript

    Download a transcript of the interview with Phil McGeevor

     

    Please connect with me

    Subscribe, rate and review the podcast in iTunes

    Rate and review the podcast on Stitcher

    Like our Facebook page

    Follow us on Twitter

  • HPH239 : 3 great eco developments in New Zealand – with Matthew Cutler-Welsh

    HPH239 : 3 great eco developments in New Zealand – with Matthew Cutler-Welsh

    Matthew Cutler-Welsh takes us through three exciting projects that are making an impact in New Zealand.

    Interview with Matthew Cutler-Welsh

    Matthew Cutler-Welsh of Home Style Green was one of our early guests on the podcast, talking about some of the challenges of creating sustainable urban systems.

    Since we last spoke with him, he has trained in building surveying. It has taught him more about building science and he sees it as a positive step that expertise in building science is generally becoming more recognised and utilised in architecture and construction in New Zealand.

    “Because what I’ve realised is that buildings are complex systems and they’re a system of systems, and the more we make them controlled environments on the inside then the more we have to understand how the various aspects of physics, basically, interrelate to each other.”

    This interest has also led Matthew to his new role working with Pro Clima, where he primarily works to educate and support both the design industry and building industry in their understanding of some of the fundamentals of building science.

    Matthew is also on the board of the Passive House Institute New Zealand.

    The Living House

    Matthew’s first choice to discuss is owned by friends of his – Rochelle and Joel. This one is unique in that as well as physically building the house themselves using rammed earth, they are also targeting the triple prize of achieving the Passivhaus standard, Living Building Challenge and Homestar (equivalent to the old Code for Sustainable Homes or LEED).

    Rochelle is an engineer by trade and is very detail focused, hunting down products and details and finding out everything there is to know about them.

    Matthew explains that as well as being an amazing home, it will be an incredible resource for the whole industry, leading the way for others to follow.

    He says the house, by pushing boundaries, is already making waves and challenging the Council. Meeting standards is generally the path of least resistance to getting permission, but for anyone trying to build a house that actually performs better they may find themselves with an uphill struggle.

    “So, if you’re doing something that falls outside of that because you want to have a house that actually performs really, really well, then you have to put in quite a lot of effort to prove to the Council that the products, systems and how everything fits together is not going to cause them any problems down the track.”

    Because they’re doing a Living Building Challenge, they are able to argue a case for not having to pay fees for Council utilities that they won’t be using. They’re finding that this is rattling a few cages!

    The design

    Rochelle and Joel are building a contemporary style of home using rammed earth. The earth is sustainable as it is sourced fairly locally, and also allows them to do much of the building themselves. While it might not have universal appeal in terms of aesthetic and time it takes to build with, it is certainly a unique product.

    Living Building Challenge

    Matthew explains the Living Building Challenge as going beyond sustainability. He says that ‘sustainable’ is just a case of not doing harm, whereas the philosophy behind the Living Building Challenge is thinking about how the environment can actually be improved by the building being there.

    “So, the building becomes an asset to the ecology and the environment around it. Rather than just taking it as how do I make this building and do less bad to the environment, how can I actually use this building as an integral part of the ecosystem.”

    One aspect is in the treatment of water, where the building systems (natural filtration systems, rain gardens etc) clean the water so that any run-off from the site is actually cleaner than the water that comes onto the site in the first place.

    Living Building Challenge also provide guidance on the use of products and materials, which can be a particular challenge in a small island nation, where you’re encouraged to use as many local materials as possible. They also don’t allow the use of some materials like certain foams and polystyrenes because of the chemical toxicity in the manufacturing process.

    Waikato House

    Matthew’s next choice is a house built in the Waikato region, south of Auckland. It was built by a builder who now works for eHaus, a national brand of Passivhaus building in New Zealand.

    Matthew explains that it stands out as being built by someone who clearly has been re-inspired and discovered a new passion.

    He describes it as a contemporary home in green pastures and farmland, that has a beautiful design and doesn’t look like a Passivhaus.

    “But it was really that passion from the builder, the pride and the beauty of the simplicity of this house that really struck me.”

    This house has been built as a show home for the construction company, and Matthew comments on how something they are seeing more of, is builders offering a “try before you buy” approach to selling houses. So instead of visiting a show home for half an hour you’re able to try it out for a night and experience first-hand how well it performs.

    Dunedin co-housing

    This co-housing group formed in 2013, and they are looking to build 20-25 houses on a 5000 square metre site, which was formerly a high school.

    The group have overcome challenges, particularly financial ones, and now have plans for two rows of terraced housing.

    Images from Architype NZ

    Matthew is drawn to this project, partly because of its Passivhaus credentials and sense of community, but also because it is addressing the affordability issue.

    “Co-housing projects like this really open up the opportunities for creating community and creating housing that works for people.”

    He sees it as an exciting project that could pave the way for future similar schemes around the country.

    Matthew highlights that there is a global community of people involved in co-housing, who have done projects successfully and are keen to help on other projects.

    And although this, and many other co-housing projects, can take a while to get off the ground, it’s actually as much about the process as the finished house.

    Find out more

    Check out Matthew’s Home Style Green podcast

    Follow Matthew on Twitter

    Find out more about the projects in this episode:

    The Living House

    Waikato House

    Dunedin co-housing

    Transcript

    Please connect with me

    Subscribe, rate and review the podcast in iTunes

    Rate and review the podcast on Stitcher

    Like our Facebook page

    Follow us on Twitter

  • HPH238 : Making Passive House homes affordable – with Adam Cohen

    HPH238 : Making Passive House homes affordable – with Adam Cohen

    Architect Adam Cohen explains how his modular construction system is making Passive House building simple and affordable.

    Interview with Adam Cohen

    Adam Cohen qualified with a Degree in Architecture from the University of Maryland 35 years ago. He was uninspired by the post-modern approach of the time, and instead was a keen follower of Ken Kern and Michael Reynolds‘ owner-built homes, and of Malcolm Wells‘ earthship movement.

    After qualifying as an architect he set about building healthy homes that used no glues or chemicals, were off-grid, had first generation solar panels and composting toilets that they made themselves. Over the several years that followed he found it a struggle to find clients who wanted to build this way so, out of financial necessity, he started a more traditional company that he ran for 20 years, employing 43 staff where they designed what they built, and built what they designed.

    “I had sold out completely”

    The company was very successful financially but it wasn’t until ten years ago when his 12 year old son started asking questions about carbon footprints and climate change that he says he had a ‘slap in the face moment’. It brought home to him that because it had been hard to find people interested in energy efficiency at the time, that he had given up his principles and was building in an entirely different way.

    That realisation gave Adam a renewed focus to “atone for all these sins. I’ve put a lot of potential carbon in the atmosphere by creating crappy buildings.”

    Finding Pasivhaus in 2008, he became one of the first people in the US to take the training. Spending a month in Europe gaining his international certification and spending time with Passivhaus builders, he returned to the US with a desire to build commercial Passivhaus buildings using a design / build methodology.

    “I realised how fragmented and dysfunctional the design and construction world really was.”

    By 2012 others had started sitting up and taking notice of what Adam and his company were doing, and were keen to seek their assistance to help other teams. However his in-house firm of architects, engineers and builders where everyone was working together, wasn’t the way the process worked elsewhere.

    Adam has made it his mission over the last few years, since selling his business, to try and help the industry move forward. He has recently moved to Canada and is helping Passive Buildings Canada put together an education programme to raise awareness that if you’re building new construction it should be done to a carbon neutral standard.

    “They need to reduce their embodied energy and they need to reduce their operational energy and then they need to offset their carbon with either credits, site generation or local generation of energy.

    We have the choice now to be proactive, or we have the choice later to be reactive.”

    The construction industry needs greater awareness of climate change

    Adam believes that in Canada, unlike the US, the federal, provincial and municipal levels are fairly well aligned in terms of being tuned in to the climate change emergency, however within the construction industry there is still not sufficient awareness from the consumers, owners, producers, architects or builders.

    He sees there being far more awareness in the European design and construction community, and the population generally, but sees the greatest potential being what’s going to happen in China in the next 20 years.

    Adam has written a draft paper called “The Integrated Modular Design Theory for High Performance,” which sees a need to move towards building with modular components that can be put together in different ways, manufactured easily and built efficiently.

    The aim is for cost parity

    Once Adam decided to divert his company’s focus to constructing healthy buildings, he realised this was only going to work if he could make an economic argument for it and get cost parity with the alternatives. In the commercial sector this wasn’t too difficult to achieve, but in residential it has taken a lot longer.

    One of the first steps was to convince people to pay more for the construction of the building, instead of a cheaper building with higher energy bills.

    “Then it became a question of, if you’re going to be paying eleven-hundred dollars a month for energy and mortgage and I can deliver a building that’s more comfortable, that uses less energy, and it’s going to cost eleven-hundred dollars a month or less…. if I could take some of that money that you’re spending on those electrons and put them into your mortgage so that you’re building equity and wealth rather than just spending money, but the net monthly cost is the same, why would you not do it?”

    After three years of mining data they were able to put forward a proposition for single-family homes, where mortgage plus energy is equal to or less with a Passivhaus than you would pay for a standard house. Initially that was hard to achieve as windows had to be imported from Europe and there were very few suitable mechanical systems, but now the US market has options available.

    Paying for an experienced team could save money

    Adam tries to encourage owner-builders who are starting out on the process to create a team of people who have experience in Passivhaus, otherwise they might end up wasting money while they learn, to the cost of the client.

    Adam has created a Lego style of system where owner-builders can buy a kit of pieces that snap together making a Passivhaus envelope very simple. Similar systems exist in the UK where you can buy a guaranteed shell and do the rest yourselves.

    Understand the inter-relation between construction stages

    Adam tries to simplify the thought process for self builders when approaching a new project, by helping them to understand the inter-relation between the different stages of the construction.

    He breaks these down into four ‘buckets’. They are:

    • Site acquisition – how much it is going to cost to buy the site
    • Site development – how much it will cost to clear the site, install utilities, do any groundworks and landscaping
    • The construction – the cost of getting the shell up, enclosed and tested for airtightness and thermal continuity
    • The finishes – interior and exterior finishes, including mechanical and electrical and everything else within the shell.

    He explains that when people have a fixed budget, he makes them understand that money can be moved around those buckets as none are fixed. There is an inter-relation between the site acquisition and site development buckets which need to be balanced, before you know how much there is left for the other two buckets.

    Within each area there will be some costs which are fixed but others where savings can be made, such as with the complexity of the design.

    “So, when you start to create your balance of how do I make all these pieces balance in this budget, I want people to understand that you need to separate out your thinking so that you understand, if I go spend a quarter of my budget on the site and then I spend another quarter of my budget on site development, so I have actually half of my budget to build the building with, is that realistic that I can actually get that building built?”

    “Start with, ‘here’s the system, now let’s design to the system’.”

    Using Adam’s Lego style system of modular construction, he explains how clients often use a free programme like Google Sketchup to help with their design. Rather than people coming up with a design and then trying to make it fit a manufactured system, this way allows clients to use the Sketchup modular blocks that Adam has created, to start their design. The manufactured products help generate an efficient form, leading to an affordable solution.

    Consider the long-term impact

    “I would hope that anybody considering a new build would try to work their way through to figure out how to build that building with the lowest impact possible. Because as a species, it’s critical that each of us make the right decision every day in everything we do, and if you’re building a building that’s going to saddle your grandchildren with ongoing operational energy that’s going to be carbon intensive, you’ve kind of just slapped your grandchildren in the face.

    I know that the millions of square feet where I’ve built really bad buildings, I’m now approaching about a million square feet of Passivhaus buildings. So, not that I’m offsetting them, but at least I’m reducing my impact long-term.

    So, I would encourage all of the individuals listening to this to consider their actions when building a new building, and how it will affect their grandchildren.”

    Find out more

    Visit the website of Build Smart

    Follow Adam Cohen on Twitter

    Check out Adam’s YouTube channel

    Transcript

    Please connect with me

    Subscribe, rate and review the podcast in iTunes

    Rate and review the podcast on Stitcher

    Like our Facebook page

    Follow us on Twitter

  • HPH237 : A SIPs Passivhaus build on a tight budget – with Richard Dudzicki from RDA Architects

    HPH237 : A SIPs Passivhaus build on a tight budget – with Richard Dudzicki from RDA Architects

    Architect Richard Dudzicki explains the tricks and challenges of designing a £500,000 house on a £250,000 budget.

    Interview with Richard Dudzicki

    Richard’s practice concentrates on residential architecture, initially with ecological buildings but now with a focus on Passivhaus. He likes the physics that tells you how the house will perform, and the results that it achieves.

    It is not uncommon for Richard to have taken on multiple projects in the same street, based on recommendations, with the Passivhaus Mews II development being one of those.

    A difficult to access site in a conservation area

    The site is off a Georgian street in an historic part of London, around the back of Camberwell Grove. The buildings on the main road are Grade II listed, and the Mews where they have built the Passivhaus falls within the conservation area.

    The ground conditions in the area can be challenging, as they are London clay, and with the numerous mature trees there can be problems with subsidence.

    The brief had to develop to include a newly purchased swimming pool

    The client was a lady in her seventies, at the time living in one of the Georgian houses but finding it too large for her needs. She wanted to take a section of the garden and build a modern, 120 square metre, three bedroom home with a courtyard and off-street parking, for £250,000.

    In order to keep down costs their first application was for a rendered exterior, but this fell foul of the planners, conservation department and Camberwell Society, who didn’t want a mock pastiche of a Georgian building, but instead wanted something of the time.

    During the development of the plans, Richard had been able to persuade his initially reluctant client to build to the Passivhaus standard. It was at this time that she also announced she would need garden space for the pre-fab training pool that she had just put a deposit down on!

    One of the biggest challenges was fulfilling the need for off-street parking, and designing it for a large, electric car that would likely be more commonplace in the future. The building envelope, being a rectangular box shape, had to have an area taken out of it on the ground floor for the parking space. With the house not being wide enough to have a garage and door, they used it as an internal courtyard outside of the thermal envelope. That meant they had a larger surface area exposed to the cold which in turn added around £7,000 to the cost for additional insulation required.

    SIPs panels were ideal for the limited access at the site

    One of the logistical elements of designing the building package was how they were going to get everything on to the site, and that’s where the SIPs panels came in. They designed it in such a way that they would be able to do it in three lifts, for a total price of £47,000 including all of the structural elements and insulation, from Kingspan SIPs Panels.

    The speed and necessary logistics for accessing the space meant SIPs were an ideal construction method, and they were able to have the whole building erected in under three weeks. The panels they used were lightweight and thin, which was necessary for the limited site space they had.

    Consider condensation if insulating on the inside of SIPs panels

    Richard gives a word of caution about insulating on the inside of SIPs panels, as you can have interstitial condensation. It’s therefore important to have a condensation risk analysis done. Putting the insulation on the outside makes it easier to adhere to and easier to deal with airtightness.

    Airtightness was tested at different stages

    Built into the contract was that there needed to be three air tests carried out. The first one was as soon as the building was erected, without the windows. Instead they taped up the windows and doors with a damp-proof membrane and tested the frame, making adjustments to improve the airtightness where necessary.

    The second test took place once the windows had been installed. The result of this test proved that the manufacturers didn’t know how to correctly install Passivhaus windows, so they had to come back and do them again.

    “Specify with whatever contract you’re using – whether it’s the window manufacturers who are doing it or whether it’s your main contractors installing the windows – that you’re clear cut and you’ve got a piece of paperwork before you’re paying for it, that these will be installed to whatever airtightness you want them to. And then have an air test afterwards and then you can cross check it. Because without that, once the windows are in and you’ve started putting the plasterboard on, you’re screwed. ”

    The contract protected the client from financial loss

    On this job they used two RIBA domestic contracts: one to cover the main building and one for the foundations. This provided protection for the client when the main contractor went bankrupt half way through the project. The client didn’t lose money from it, but they did lose around 4 months of time while the contracts were sorted.

    A £500,000 house for a £250,000 budget

    The client wanted a very palatial feel for the interior, so a lot of time was spent looking at what she wanted and then working out how to substitute materials to bring it within budget. One way of saving money was to build the staircase out of MDF and paint it white, to give the effect she was looking for. 

    The kitchen was imported from Italy, and even with the 2000 Euros delivery fee, worked out to be a good deal. 

    Richard advises against buying individual pieces on eBay, because unless you have a very cheap facility in which to store them, storage is going to be a problem. 

    A chunk of the budget did have to be spent on a few bespoke items, like the front garage doors that roll back, and the garden deck that slides back to reveal the swimming pool. 

    One of the other complex issues on this building was making the rooflight work without spending silly money. They achieved it by developing a system of sitting the rooflight in a foam glass sandwich. It also wasn’t helped by the original builder having installed double glazed units instead of the triple glazed that had been specified. They got round this by putting in a further double glazed unit to create a quadruple glazed rooflight. 

    “The other thing that’s important with anything where there’s a tricky situation like Passivhaus, for instance, or anything with complexity – Passivhaus isn’t complex. It’s more a question of keeping an eye on the builder. What I mean by this is be careful when you go to site and make sure that you’ve got someone who’s got experience, who’s cross checking what the builder is doing. Because if you move past the stage where it’s too late to fix it, that’s where it can get really expensive.” 

    Be strong and stick to your ideals

    There was many a time that the client had doubts about Passivhaus and wanted to leave it, but Richard stuck to his principles. Thankfully the client now loves it and proudly shows off her house at Passivhaus open days. 

    In terms of what Richard has learnt from this job, “I suppose for me as a practice, don’t listen to clients when they come up with builders ideas if you’re not very sure that the builder is any good.”

    As a practice Richard thinks they probably made a loss on this job as all the R&D on the project probably amounted to three-times the number of hours that they actually charged for. Richard however considers it a research project from which there was a huge amount of valuable information they were able to benefit by. 

    Richard explains that the physics of Passivhaus is about 10% of the challenge, but making the house work for the client makes up the rest. There are many questions that he says a client needs to work through, rather than just thinking ‘I want to design myself a Passivhaus’. These would include how many children will live there, how long you plan to live there, whether it’s going to be left to your children, the longevity of the house, whether it needs a ten year warranty, etc.

    “And one of the things I have learnt from this… is Passivhaus is a fantastic system but don’t let you be swayed by just Passivhaus rules, regulations and what you can and can’t do. Basically, you can do anything as long as you’ve got an architect who understands what Passivhaus is about. You can design pretty much any sort of building you want to and apply the principles to it. And I think that’s really important.”

    Find out more

    Visit the website of RDA Architects

    Follow RDA Architects on Twitter

    Transcript

    Please connect with me

    Subscribe, rate and review the podcast in iTunes

    Rate and review the podcast on Stitcher

    Like our Facebook page

    Follow us on Twitter

  • HPH233 : How to choose a construction system for a house build – with Mike Hardwick

    HPH233 : How to choose a construction system for a house build – with Mike Hardwick

    Self build consultant, Mike Hardwick, explains the pros and cons of different construction systems.

    Interview with Mike Hardwick

    Mike hasn’t followed a typical path into the industry. He actually worked in the RAF for 26 years, and with all the different postings came many different house moves for him and his family. Deciding to settle in one place they selected a location (based in the middle of where possible future postings could potentially be), bought a plot of land and built their own home.

    Mike often found himself propping up the bar in the Officers’ Mess answering questions about how to build your own home. When he came out of the Services in 2005, he realised that what he would really like to do was get more people interested in building their own homes, and at that point decided to make a business from it.

    The first series of Grand Designs – copyright Channel 4

    Mike’s house build coincided with the first series of Grand Designs

    They bought the land for their self build in 1999, got planning permission in 2000 and in 2002 were able to move in. Doing the build in parallel with the first episodes of Grand Designs often left them able to empathise with the self-builders, pick up a few tips or wonder why they were doing things a certain way.

    Mike credits Grand Designs for redefining the scope of self build, making people realise that it doesn’t have to just be for the very wealthy. Although he does concede that the TV programme “Sensible Couple with Reasonable Budget Build Modest House On-time and On-budget with a Competent Builder” is never going to get commissioned!

    A build system is the structural element of the house

    That is, what it is built from and held up by. “And the confusing bit with a build system is that just because what’s on the outside of a house looks like maybe a brick, it doesn’t necessarily mean that it’s a house made out of bricks structurally.” Most, but not all, houses in the UK are built with a twin-leaf construction, where the inner leaf does the supporting work and the outer leaf makes it look pretty, with timber, brick, tiles etc.

    As well as holding up the structure of the house and being the main material used in the construction, it is what the services run through and are bolted to.

    As such, getting the right system for you is going to be an important decision to make, and generally it’s entirely your choice. Because the building system you use doesn’t usually dictate the external appearance, the planners aren’t interested. So as long as Building Control are happy that it will comply with regulations then you are free to choose.

    Price comparisons aren’t straight forward

    Mike explains that people will always ask him which system is the most cost effective, but drawing a price comparison is actually quite difficult. He does say that there is a fairly narrow band of cost when it comes to the different build systems, and what influences the price most is actually the detailing and the finishes that go on inside.

    What really hikes the price is when you trade in the materials for speed of construction, such as with houses that are pre-fabricated and then erected on site in a matter of days.

    Masonry construction

    Mortgage companies for example will typically ask whether the house you’re buying is of masonry construction with a tiled roof. They like it because it has substance to it, it’s a safe thing to invest against, and will be appealing to potential future purchasers.

    “It’s the way that we’ve trained our builders, it’s the way we’ve been conditioned to think about how houses work, and it’s what we fall back to. So, they’re easier to insure, they’re easier to mortgage against and they’re easier to sell. Which is why people still do it.”

    If you’re working to a modest budget, then using brick and block is generally at the lower end of the cost spectrum, so is likely to be a baseline for constructing your own home. They are quick and easy to build, relatively cheap to buy, and are easy to handle and cut up. They tick the boxes for mortgage companies, insurers and builders.

    Other positives are the strength they provide, that you can put beam and block floors in. The thermal mass provides a stable temperature throughout the house, and the masonry affords you flexibility of design. You can build just about anything you want in masonry, and combined with steels can give you large, open spans.

    Traditional breeze blocks were made out of cement covered cinder. Modern blocks are lightweight and made from pulverised fuel ash, so the detritus from a coal-fired power station mixed with resin and turned into a block. The aerated middle traps air and provides insulation, and also makes them lighter.  In the UK there is currently a shortage as there aren’t many coal-fired power stations remaining, so the raw materials have to be imported.

    Timber frame

    Timber frame basically replaces that breeze block element with a structural framework of timber. It is associated with being environmentally friendly, high quality, accurate off-site manufacture. It is efficient, effective and with the speed of construction it makes for an attractive proposition.

    Whereas masonry has high embodied carbon in the manufacture, timber frame is carbon neutral in that you plant a tree, chop it down and plant another tree. Timber is also a flexible material in that you can build the walls, ceilings, floors, windows, doors, stairs etc from it.

    Mike is keen to point out to people who worry that building a timber frame system might suffer from problems such as termites or rot, that probably around 65% of what we would call a masonry house is actually made from timber anyway, being the roof trusses, stairs, skirtings and so on.

    Mike concedes that, if pressed, he would say timber frame is probably the cheapest way of building the structure of the house. But that would only be if you were doing the most economical and basic timber frame with no frills, and without doing anything to attenuate the acoustics. Most self-builders would want to go above and beyond building regulations and put in good sound-deadening insulation to minimise noise transmitting through the house. When taking into account the extra money on the sound-proofing, you are probably then looking at a more expensive path than masonry.

    “Now, if you want the environmental stuff but you don’t want a lot of noise transmission, timber frame with noise attenuation is a good thing but it’s going to cost you more than it will for a masonry house straight out of the box. This is where you need to start doing your homework and making your calculations about what you actually want, how you’re going to live your life, and what you’re trying to get from the home that you’re building.”

    The thing to remember with timber frame is that it will last well as long as the moisture content in the structure is kept to a minimum, and allowed to escape so that it doesn’t build up. On the inside of the house behind the plasterboard there will be a non-breathable, vapour control layer. This stops any moisture occurring inside the property from getting into the structure. On the external wall, underneath the render or brickwork, is a breathable membrane, allowing any moisture that does get inside to find a way out.

    Insulated Concrete Formwork (ICF)

    These are a type of fire retardant polystyrene foam block. They fit together to create a solid outer wall and a solid inner wall, with the gap in the middle being filled with poured concrete. When the concrete sets and cures, you end up with a waterproof, insulated, monolithic wall which is highly insulated, highly airtight and with the strength and density of a masonry wall. This makes it popular for people building to the Passivhaus standard.

    It also benefits from being very quick to construct, you don’t need to be too skilled to put it together, and being waterproof is a good choice for flood-prone areas.

    Some people aren’t keen on this method because of the perceived embodied carbon being quite high. In reality, Mike says, they are mostly made of air with very little actual structure to them. There are other alternatives, such as Durisol blocks which are much the same in principle but use chopped up timber instead of the polystyrene foam as the insulant.

    Although there is a lot of concrete used, Mike suggests thinking about the amount of energy that the structure saves straight away with its high levels of airtightness and thermal performance.

    It is worth thinking about future use, as putting in more doors or windows for example at a later date is going to be very difficult. Also perhaps a marine ply or a Thermacell type board is advisable for indoors when there might be considerable weight such as cupboards or TVs to be hung from them.

    Structurally Insulated Panels (SIPs)

    These are manufactured off-site and built of two oriented strand board (OSB) sheets that are filled with expanded urethane insulation foam. The panels can be cut, shaped and fixed to other panels to make a complete housing structure. They tend to be accurate, airtight, watertight and put up on site very quickly.

    If you were thinking of using this building method, you would take your designs to a SIPs company whose CAD systems would create the plans to feed into the machines that produce the panels to millimetre perfection. These panels work with the other panels around them, and can even have steelwork in there for covering large spans, to give the structural integrity to the house.

    Mike explains how the success of a masonry constructed home is very dependent on the quality and skill of the bricklayer. With ICF it’s harder to go wrong, as the panels are designed to fit together at 90 degrees, meaning the walls are going to be straight and it will be easier for fitting out afterwards.

    One drawback is that you can’t later decide to move things about or add doors or windows because the structural integrity will be compromised.

    “The advice I would give to anyone contemplating building in SIPs is to spend a really long time thinking about what you want and what’s going to go into your house, and the design of your house, and then say, ‘that’s it, no more changes. We’re happy with this. Go and provide this house.’ Because once it goes into the computer and they pull the handle, then that’s what you’re going to get. If you suddenly say, ‘about that wall there, can we have another one here or another window here? Can we have that door moved to the left?’ that’s going to be expensive, it’s time consuming, you’ve got to start again and recalculate the whole thing in the worst cases.”

    In terms of cost, Mike says ICF and SIPs used to have roughly a 10% premium on them because there were new factories to be paid for, but as they are becoming more common-place the prices are more competitive. Some manufacturers are even assuring that they can produce a house for about the same cost as brick and block.

    Straw bale

    Previously seen as something you wouldn’t consider for mainstream building, nowadays the increased focus on energy efficiency, natural materials and environmentally conscious building has given straw a greater appeal. Mike explains that structural straw bales, as opposed to ones you would buy direct from a farmer, are processed and compacted to form dense blocks.

    “When you encapsulate this within a lime water and plaster that you would normally be using with this build, you’ve got something which has got no oxygen. So, it doesn’t catch fire. It doesn’t. It’s just a really good carbon neutral method, environmentally friendly way of getting all that insulated wall which looks really good as well.”

    Straw bales do mean that you end up with thick walls, but for some people that is a positive feature. The deep window and door reveals combined with the lime plaster make it look and feel like a solid house with a natural, rustic feel.

    Mike concedes that some mainstream lenders and insurance companies might not be keen to deal with these, but others like the Ecology Building Society see the benefits and will lend against them.

    Prefabricated system builds

    Most of these factories tend to be in continental Europe where the prefabricated kit is made and then brought to your plot to be assembled. This method probably won’t suit those on a smaller budget but for projects on a grander scale, or at least a grander budget, they will be rewarded with superb, quality finishes.

    “And for those people who want to be hands-off with the self-build rather than actually getting involved and really worrying about how the bricks go and how the timber frame is constructed, they can sit back and basically say, ‘here’s the house I want. Build me one of those. Here’s where I want it.’ And somebody else goes and does it for you. You pay for the privilege of doing that, but the stress levels are going to be a lot lower than somebody who’s actually project managing their own build all the way through.”

    Again, this is a system where decisions need to be made up front as any changes later are going to be extremely costly.

    Steel frame

    A steel frame self build house wouldn’t be commonplace in the UK. They tend to be more popular in warmer climates. If you have a steel structured house and are trying to stop cold-bridging then you’re starting from a losing position.

    However, recent changes in planning regulations, where permitted development allows people to take farm buildings and convert them into residential dwellings with less of the hassle, has made extensions and renovations of steel-framed farm buildings more common.

    Thin joint

    The masonry industry has recognised some of the problems of building with blocks (weather dependent, speed of construction, reliant on quality of the builder) and come up with a variation on the masonry theme called Thin Join. They use over-size versions of the cinder blocks and instead of using a 10mm sand and cement mortar base, they are held together with a type of glue adhesive.

    “But by taking out things like the mortar bed, you’re taking out two things. One is a passage for air to get through, and when air can get through, noise can get through. So, by taking that mortar bed out, you’re putting better airtightness into it, putting more insulation into the wall and you’re taking away some of the need for skilled construction to put it together”.

    It’s also a cleaner system, using a bucket of adhesive instead of having piles of sand and cement spreading around the site.

    Which system to use depends on what is right for your circumstances

    “So, if low cost is your priority then you need to be looking at the traditional masonry or the timber frame setup. If you’ve got family and you want a bit of peace and quiet, you want some separation of noise, acoustic attenuation, then the masonry end is probably the way you want to be looking at.

    If you want energy efficient, you’re environmentally aware, then you want high efficiency and low running costs. Then timber frame is probably where I’d be looking at. That’s at the lower end of the spectrum on there.

    And as you go up the performance scale, that’s when I’d start looking at the ICFs and the SIPs panels. They might cost you a little bit more to build but again, there’s a trade-off there against the cost of the materials and you need less labour to put it all together.

    At the very top end, if you really are a hands-off builder and you want the sort of quality which just comes with that continental standard, then these system builds that we spoke about, hand over the money and let these guys come and build it. You’ll have a house which will be good enough to feature in the magazines. But you will pay for that privilege.”

    Additional resources

    Build It Magazine

    NaCSBA

    National Self Build & Renovation Centre

    Transcript

    Download a transcript of the interview with Mike Hardwick.

    Please connect with me

  • HPH231 : How to design an interior for a modern home – with Gabrielle Blackman

    HPH231 : How to design an interior for a modern home – with Gabrielle Blackman

    Interior Designer Gabrielle Blackman explains how, when planned properly, good interior design should take the owner’s personality and stamp it on the house.

     

    Interview with Gabrielle Blackman

    Gabrielle Blackman trained as an artist and found that with interior design she was able to combine that with her passion for being hands-on, busy and working with people. Her career has seen her work in interior yacht design as well as with some of the leading designers around, before taking the step of starting her own company.

     

    The line between interior design and architecture can cause on-site conflict

    The use and practicality of the house can sometimes come into conflict with the architecture.

    “So, an architect might want a floor-to-ceiling piece of beautiful glass, so you’re celebrating the space of the room and all of this wonderful natural light, and then I come in and say, ‘where are we going to put the furniture? How are we going to store stuff?’”

    Gabrielle explains that there is always a bit of give and take involved and often some heated discussions, but it’s a healthy and robust relationship which as a result produces the right house for the client.

    “But we get something amazing at the end of the day because it’s two skills that slightly butt heads, but you create something beautiful.”

     

    It should feel full of personality, be incredibly practical and look amazing

    Gabrielle believes that a good interior designer should be able to interpret their clients’ personality and stamp it on a building. What is also important is that the client feels immediately natural and comfortable within it, and not as though they are in a show home. That is something that comes about through the collaboration process.

    “All the details that might be overlooked by exhausted clients who are under a barrage of decision making every day and having to deal with contractors, an interior designer should be able to come in fresh and fight for the extra details that makes it so lovely.”

     

    The initial process is the same for every job: space planning and layout

    Gabrielle has developed this process and follows it for every job, no matter how large or small, traditional Georgian home or new build Passivhaus, and it is based around space planning and layout. She builds a picture by understanding her clients’ needs, finding out: where the furniture is going to go, how they are going to use each room, whether they have children or pets, whether they work from home, etc.

    So the basis of any good design has to start with the layout, ie the way the space is going to be used, how people are going to move around the house, and what they need to keep in each room.

    From there, a plan can be produced for the electrical, lighting, plumbing and heating layout. This is why it is essential to consult the interior designer at such an early stage, before the trades are involved, so that radiators aren’t already in the place where a TV or sofa needs to go!

     

    Create mood boards to develop ideas

    Once the practicalities of how the house is going to work, the room layouts, and plumbing and electrical plans are sorted, the next step is to think about how you want it to look.

    Gabrielle often uses Pinterest to communicate with clients and create mood boards for each room. She creates concept boards which are linked to the Pinterest boards, and which are then linked to the actual products. For clients making their own purchases this provides a quick and easy way of shopping for their selected items.

    Even if you’re not using an interior designer, Gabrielle recommends using Pinterest to create your own mood boards by finding inspirational images that you love and then start pulling out the key elements from that to make your board.

    Gabrielle tends to use one big inspirational image that gives the feel of the room, and then surrounds it with the actual items that are going to be put into the room, ie a table, a lamp etc.

     

    The whole house should have a united feel

    That’s not to say it all needs to be painted the same colour, but running the same flooring through each floor can create that feeling for example.

    In Ben’s house, Gabrielle noted how the snug needed to have a different feel, ie the winding down and having space for the evening, as opposed to the natural light of the large open spaces. For this they used a dramatically different paint colour to make it feel cosy and cocooning.

     

    Don’t compromise on floors and doors

    With any project it is important to set your budget and work out what you want to prioritise as early as possible. If the budget is going to be tight, Gabrielle recommends making sure that you have a good floor and doors – the bones of the house – so you have no regrets later on, even if that means having basic or little furniture to start with as that can always be built up over time.

    In Ben’s house they chose a beautiful herringbone floor which becomes a feature in the open, uncluttered space.

     

    “Working with fantastic trades will make a house”

    Gabrielle suggested getting bespoke storage made, and Ben was fortunate in that the building company he used had very talented carpenters.

    “What I love about bespoke joinery is it will never go out of fashion. If you do some really beautifully made but simple built-in shelves and cupboards, you need that storage anyway. Every family needs more storage than you can ever imagine, and cupboards are just the source of all happiness, so that’s great. And having them beautifully made, it just means you’ll never be bored of them.”

     

    The right interior designer should add value to your project

    Gabrielle stresses that it is important to choose an interior designer who you feel you can communicate with, and who understands you. There should also be a fee structure that you’re comfortable with, for defined chunks of work, and not just an open cheque book. It is something that needs to be budgeted for like every other part of the build.

     

    The finishing touches can be equally fun and stressful

    Gabrielle has joined Ben at the house for working out the finishing touches. She likens this time as being at the end of the marathon when everyone’s a bit tired. The house needs to have the final styling and dressing which is where the interior designer can give help and reinforcement. Together they have searched through Ben’s existing belongings to see if there is anything that, coming at it with fresh eyes, they might have forgotten about which actually will look wonderful in their new home. And then it’s just a case of deciding on the few more pieces needed to finish it off.

    Some images taken before and after Gabrielle’s visit

     

    Key tips:

    • It’s your space – don’t be afraid to make unpopular decisions.
    • If you’re being pressured into something because it’s easier for the build, or if in your heart it doesn’t really feel like you, then stick to your guns.
    • Measure everything!
    • Be confident in your tastes – you are the expert on you.
    • Make sure you prepare: get your mood boards and layouts done before you even meet your builder for the first time. Including everything such your chosen doors and floors will mean a more accurate quote.

     

    Find out more

    Visit the website of Gabrielle Blackman

    Follow Gabrielle on Twitter

     

    Transcript

    Download a transcript of the interview with Gabrielle Blackman.

     

    Please connect with me

  • HPH230 : What is lime render? – with Martin Brown from Best of Lime

    HPH230 : What is lime render? – with Martin Brown from Best of Lime

    Martin Brown explains how this ancient material can be used in the modern world.

     

    Interview with Martin Brown

    A decorator by trade, Martin spent time working in the family business specialising in handprinted papers and on traditional buildings. That led him towards lime plaster with a particular interest in some of the old, traditional mixes that have been lost. He has been running his Best of Lime company since 2014.

     

    Lime is a binding material

    Lime is burnt calcium carbonate. Chalk, limestone, shells can all be fired in a kiln to make quicklime which you then slake (combine with water) and use as a binder.

    France has a long tradition of manufacture, with the Bordeaux region being a big producer, and in the UK large quantities are made mostly in the Buxton area, but also in Lincolnshire which produces more of a chalk lime.

     

    It uses a lot less energy to make than cement

    Martin believes that lime has a number of advantages over more modern materials.

    For a start, cement is fired at 1300 degrees, whereas lime is between 900 and 1000 degrees, making it a more sustainable product.

    Aesthetically it is arguably more visually attractive, it is more flexible and is more breathable allowing free transport of moisture through the building, creating a healthier environment.

     

    Different additives provide reinforcement

    Lime has been used as a binder for several thousand years, albeit with different tweaks and additives to make it perform differently. And while recipes from the 1830s that included bone ash, urine, beer and cheese in the mix have thankfully been superseded, animal hair, which acts as a reinforcement, continues to be popular! Horse hair is popular but cow hair is evenly more commonly used, particularly in the chalk plasters of East Anglia. A sand and lime mix on a green oak timber frame will crack and fail as the frame twists and shrinks, but a lime and chalk mix with lots of cow hair gives a mix that has plenty of flexibility. It can also be applied very thickly, and stands up to the rigour of both hot and cold temperatures.

     

    Some plasterers see it as a dark art!

    Martin’s aim at Best of Lime is to bring an ancient material into the modern world, and make it perform as well as, if not better than, modern materials. For this to happen it also needs to be easy to mix and apply.

    All their plasters can be mixed using an ordinary plasterer’s paddle drill or standard bell mixer.

    The dry mix is combined with water and a separate bag of fibre reinforcement. The fibre they use is 3 denier, which equates to around 280 miles of fibre per 25kg bag.

    Having that much fibre is something that couldn’t be achieved with traditional methods such as animal hair or screeding fibres which are much thicker. It is mixed into the top coat where, thanks to it being so fine, it isn’t seen.

    Lime lends itself to rounded corners because it’s a softer material, and the slower setting means there’s time to mould it into the desired shape.

    “It has an organic soft aesthetic to it. So, when it is finished, it has a much softer look to it. And of course, you’ve got the mechanical side of it being a much more lightweight, less dense material than sand and cement. You don’t need to have movement joints everywhere. So, you have a much more traditional look to a building without big mastic joints all the way down it.”

     

    Keep an eye on the weather forecast!

    With proper planning, even if there is inclement weather the plasterer will hopefully have jobs still to finish off inside the building. While the autumn is a busy period for getting work done before the weather turns too cold and wet, modern work programmes don’t tend to allow for downing tools until the Spring. It might be that a ‘tin hat’ approach to covering the building is required to keep the rain off.

    “So, getting the plaster to dry outwards, especially if you’ve got a building where it can’t dry inwards, if you’ve got a particular background that doesn’t suck the moisture back in, then we have to look at air movement, warm air if possible, covering in scaffolds. There’s lots and lots you can do but in the end, it’s all water based, and keeping water off.”

    Martin says that his products stand up to being applied in extreme high temperatures, but that it’s usually the plasterers who will give up in the heat!

     

    There are a variety of colour options

    The colour of lime is mostly dependent on the aggregate that it is being used with, and this can vary regionally. A mix using a very white sand will make a very light finish, whereas towards Norfolk there is a tendency for a more brown effect. Martin uses a lot of chalk which makes a neutral, creamy off-white plaster.

    For different colours, aside from decorating it afterwards, tints can be used although this isn’t something Martin recommends as there’s greater potential for problems. Any slight change in aggregate colour for example might show on the finished product.

    For a traditional finish, a limewash can be used, either with or without added pigment. There are also modern silicate paints which look and perform more like a masonry paint, but have the important characteristic of being breathable.

    In terms of maintaining the finish, the durability will be dependent on exposure levels and detailing around the building. The limewash will gradually wear away so may need to have another couple of coats within four or five years.  In more sheltered areas it may last much longer.

    There are also clear, breathable coatings that can be applied if there is a requirement to maintain the natural colour of the plaster, which help with water shedding and keeping the dirt and organic growth at bay.

     

    They are unable to compete on price with sand and cement

    However, one of the advantages they have is that work can generally be done in two coats. For sand and cement, if the traditional look of rounded corners is required they tend to use three coats, so what you lose in money on the material, you gain with the labour saving.

     

    Find out more

    Visit the website of Best of Lime

    Follow Best of Lime on Twitter

     

    Transcript

    Download a transcript of the interview with Martin Brown.

     

    Please connect with me

  • HPH229 : How do you build a straw bale house? – with Barbara Jones

    HPH229 : How do you build a straw bale house? – with Barbara Jones

    Straw Works co-founder Barbara Jones explains the different methods of building with straw.

     

    Interview with Barbara Jones

    Having trained in carpentry and been involved in the construction industry for many years, Barbara took a year out in 1994 to consider environmental issues and how they were being approached in other countries. A two day course for women in straw bale building in California sparked her passion.

     

    Four different approaches to straw bale building

    • The original approach, called the Nebraska Style, is a load bearing method that has no frame at all. The structural ability of the straw to take the weight of the floors and roof is used to make simple buildings of up to two or three storeys.
    • Following that, many timber frame buildings adapted to using straw as an insulation block. These are called in-fill buildings.
    • The hybrids are a mixture of different techniques, combining in-fill and load-bearing. An instance where this might be used is if a south wall was all timber and glass then the rest could be load-bearing.
    • The fourth method uses pre-fabricated straw panels. They could have a place in the mass market thanks to their ability to make modular houses very quickly and assemble on site in three or four days.

     

    Straw panels have wider appeal

    Barbara is working with a company in Lithuania, Ecococon, which is making the straw panels to a high standard. They use large round bales which are unrolled in the factory, and using a machined process are transferred into a wooden box and packed to a very precise density and moisture content. Barbara uses the distinction of it being straw in a box, rather than a straw bale in a box. The boxes can be made into different sizes and shapes of panels, according to the design of the building. Being an engineered frame makes it simple to build with, thus appealing to a wider clientele, and it also meets Passivhaus standards.

    Once on site, the walls of a three bedroom, two storey house can be erected within three or four days.

    Despite being based in Lithuania, the lower costs of production there mean it is a cost-effective way of building. Barbara believes they are able to compete on an even footing with masonry and timber frame houses, but that they are offering a better product: better thermally and also more durable.

    “They’re warm, they’re cosy, they’re peaceful and they just make you feel good. They’re comfortable. It’s something that is really hard to quantify in this world where everything has to be done by science, but if you talk to anybody who lives in a straw bale house or who’s spent some time in one, they all say the same thing.”

    “They’re not soulless and they’re not too small, like people say about modern housing.”

     

    Good quality houses for ordinary people at ordinary prices

    Being passionate about this principle, Straw Works approached Dragons’ Den for investment, realising that what they were asking for was more of a philanthropic gesture than a credible return for the Dragons on any investment. Although the Dragons didn’t invest, they did succeed in raising awareness and have a number of people interested in helping them on their journey, and particularly to move into the social housing sector.

     

    Keep it simple

    Barbara suggests one way of getting round the difficulty of finding land, is to join with community land trusts, and co-housing and housing co-ops. After that it’s a case of thinking about your design, the type of building you want, whether you are going to build it yourself or get someone else to do it, and what your budget is. Also bear in mind the benefits of keeping to a simple form.

    “What we always say to people is try and imagine something that is enough but no more than that. I think that’s quite a hard thing in this culture, to be sufficient and not exaggerate things….Keep it simple, keep it small and design it so that you can add extensions on if you need them later. But just build for your needs as they are now.”

     

    Not all bales are suitable

    Good bales for building are ones that are dry, reasonably dense and uniform in shape. Despite surities from farmers as to the quality of their bales, it is always wise to take a look at them yourself, pulling out 10 random ones to check they are suitable.

    It’s good to find ones that are baled by big contractors who are using modern machines. They’re selling by weight rather than number of bales, so the bales tend to be very dense. Also make sure the straw is long, which ties the bales together well, and not too short or brittle.

     

    Car tyre foundations are cost effective

    Although any type of foundation can be used, Straw Works encourage a totally natural package and in particular like to use car tyres. Recently they helped a community building project, a church in London that is the biggest building in the world with car tyre foundations. Filling them with pea shingle they saved the church £100,000 against the cost of what cement foundations would have been.

     

    Bales are compressed as far as they will go

    One of the guiding principles of building with straw is that it should be raised off the ground, by a minimum of 300mm, but preferably 450mm. That’s partly achieved with the tyres, and then on top of that is a structural box beam made of timber, with durable timber on the outside, and then the bales on top of that.

    For load-bearing, in-fill and hybrid methods, they use the densest bales they can and then compress them further so they end up with a density of around 100-120 kilos per cubic metre.

    They use standard details for going around windows, but don’t use sticky tapes as they don’t believe the glue will last as long as the houses. Instead they have windows flush with a timber sub-frame, then covered with wood fibreboard which helps with any possible thermal bridging, followed by a lime plaster and a linseed oil mastic seal between the plaster and the timber window.

    Load-bearing houses are held together by structural ring beams. There’s a base plate at foundation level, a wall plate at first floor level, and a roof plate at eaves level, with the floors and ceilings hung off those.

     

    Weatherproofing, not waterproofing

    The whole wall system must be breathable, so generally the outside would have a lime plaster, which is also very good at preventing water ingress. Initially it has to be protected for two or three months until it builds up that ability.

    Inside they use either lime or clay plaster. Clay plaster is particularly user-friendly and time-rich self builders can even make their own by digging it up from somewhere.

     

    Moisture can escape from the building

    Being a healthy house is a feature of their buildings. The indoor air quality is good because nothing toxic goes into them, and the paint, plasters and straw are all breathable materials. That means that there’s a movement of moisture from inside to outside all the time because of the negative air pressure generated by inhabited houses.

    Moisture doesn’t penetrate into the house from the outside.

    “We’re talking about movement of vapour, not movement of moisture. Most people don’t really understand what that means. It’s not water, it’s not steam, it’s molecules that are so tiny you can’t imagine them. So, it’s not things moving through like you’ve got water or steam somehow that could condense. It’s not like that. It’s at a vapour level, a molecular level. Unless you’ve got a house that’s been standing empty for a while, the movement is always from inside to outside. That’s why empty houses get damp whatever they’re made of, because it starts coming the other way.”

     

    Not an advocate of Passivhaus

    Although Barbara does like her buildings to be high quality, airtight and with good details, she does think “it’s all gone a bit mad and too far and too techy.” She is not an advocate of Passivhaus or MVHR but likes to be building to a level just under needing an MVHR, which means to an airtightness of five air changes per hour, although some of her buildings have been much less than that, even without the use of tapes.

    “Gas costs a quarter the price of electricity and these passivhauses are all run on electric. They don’t have gas anything. So, the sorts of savings that we’re able to make in the UK are not the same as the savings they make in a country like Germany where their electricity price is a lot lower.” “I have talked to people who are not really saving that much more. Yes, they don’t have to pay much money on heating, but they’re paying a lot more on cooking with electric and on the running of the MVHR.”

     

    Straw Works provide teaching and consultancy services

    Straw Works services include design and planning, consultancy on straw bale projects and building regulations, and training in straw bale building and natural plastering.

    In terms of the level of understanding required to self build a straw bale house, Straw Works run courses which cover the basics of what is needed. There are one day theory courses designed for people at the start of their journey and covering what planning permission requires, what you have to do for building regs, other service requirements, engineering, site surveys, what to expect if you’re building your own house versus if someone is building it for you under your direction, and why thinking about straw bale as the heart of the design is so important.

    Then there are courses covering details, such as window details and how to build the roof first, even if you’re doing load bearing.

    There is also a one day course just about plasters – clay and lime, why you should use them, what their properties are, where you can get them from and how you use them.

    As a school they also run courses on car tyre foundations and carpentry where they will follow a curriculum, and sometimes have volunteering opportunities on projects too. For the volunteer projects they always make sure there is someone very experienced leading the volunteers.

    “But I would really, really like to see mass housing in straw and I’d really like to see the little tiny buildings that we do, the garden buildings, take off. Because that really is the way that we’re going to keep the school going, by finding an income that can make it possible for us to offer bursaries to people. Because we’re in the field of private education at the moment and I’d like to see accreditation for our courses.”

     

    Find out more

    Visit the website of Straw Works.

    Follow Straw Works on Twitter.

    Find out more about Barbara’s book: Building with Straw Bales.

    Read case studies about North Kesteven Council Housing and Norfolk Straw Bale Passivhaus.

    Listen to our podcast with Andrew Goodman, Architect for the UK’s first load-bearing straw bale Passivhaus home.

     

    Transcription

    Download a transcript of the interview with Barbara Jones.

     

    Please connect with me

  • HPH227 : What’s the best way to build an airtight structure? – with Paul Jennings

    HPH227 : What’s the best way to build an airtight structure? – with Paul Jennings

    Air leakage expert Paul Jennings looks at how best to achieve that all important airtightness when using particular construction methods.

    Interview with Paul Jennings

    Paul Jennings is an air leakage expert with over 25 years experience. In our previous interview with him he explained how to achieve airtightness in low energy buildings. He also appeared in our documentary “The Future of Housing – and How Airtightness Can Help”, taking a look at housing construction quality and building performance to see how they could be improved.

    For this podcast, he looks at some of the issues with achieving airtightness in different construction types.

     

    Cross Laminated Timber (CLT)

    Paul recently tested a bungalow that was built using Cross Laminated Timber. The airtightness is essentially in the timber, and in this bungalow there were up to 8 laminations in each of the panels. The roof was a sandwich panel with layers of lamination, insulation, and more laminations on top. With the panels being larger than standard OSB boards, there is less taping involved. Each panel is also very strong, and strengthened further when screwed together. The taping goes where the panels butt up to each other, around windows, ventilation ducts, sun pipes etc. Once you have taped to the timber you have airtightness.

    Paul is starting to think that there is no need for a membrane on the outside. The CLT doesn’t meet insulation values but he thinks it’s perhaps easiest to insulate it externally and make it airtight on the inside.

     

    Structural Insulated Panel Systems (SIPS)

    Paul has experienced very good results with SIPS panels, which he feels have the potential to be very airtight. So far he hasn’t seen anyone using the airtight OSB as one of the faces of a SIPS panel system, which he thinks could improve it further.

    He explains there is a difference in results depending on whether foam is injected into the pre-made box, or whether a piece of foam is cut and put into a section of wood which then has sides added. The latter won’t be as airtight.

    SIPS panels can be a problem on site if they get saturated with water as they take such a long time to dry out, and the airtightness tapes do not adhere properly.

     

    Masonry Construction

    Masonry construction ticks the box of being a system that normal builders are used to building, where most materials can be sourced from a standard builders’ merchant. Paul offers Denby Dale Passivhaus as a great example of this.

    Paul explains that any construction with a cavity in, is a weakness for airtightness. If air can move laterally it can get around things and leak where you wouldn’t expect it to. He prefers a masonry build that has a masonry wall which is ideally wet plastered for airtightness on the inside, with insulation and render on the outside.

    “Because at that point, you have to have a continuous hole from the inside to the outside. You can’t have a hole through the inner leaf, then air moving in which way it likes in a cavity and then coming out somewhere else. It’s more robust for airtightness.”

    Paul points out that almost every masonry build has a timber frame roof, so as soon as you’ve opted for masonry construction you’ve doubled the number the number of build forms in your house anyway.

    Paul emphasises how the more complicated a build is, the harder it will be to achieve the airtightness. There is greater scope for people on site getting confused, doing the wrong thing or not checking details properly.

     

    Modular construction

    This isn’t a widely used construction method in the UK but there are increasing numbers of companies trying to develop it. The benefits of this method are that production has less of an issue with weather, shortage of trades people etc, than for on-site construction. The ones Paul has seen have been generally at a prototype stage with initial positive signs and great potential. He believes they will have to be built to be incredibly robust, as otherwise they wouldn’t survive being craned on to a lorry, driven to the site and craned off again.

    One of the big advantages of modular construction is there is less time spent on site, which means less financial impact from weather delays, and less overheads on things like site supervision, site cabins and toilets.

     

    Airtight OSB is gaining in popularity

    The trend that Paul is seeing at the moment is that membranes are losing out to the airtight Oriented Strand Board (OSB) and, for refurbishment particularly, to blowerproof paint. The most popular he currently sees in the market, and which he thinks are proving to be very successful, are the Durelis and the Propassiv.

    “At the same time, the refurbishment market is a bigger market than the new build market. We need to tackle refurbishment and we need to tackle it better. And we’re not. We’re learning lessons but really we’re taking our time over getting it and I don’t think we can afford that time.”

     

    Choose the right tape for the job

    Choose the right manufacturer, and the right tape. For example, don’t try and use 50mm tape to cover a gap of 60mm. Choose one that is wide enough for the gap.

    Paul believes the two best products for airtightness are produced by SIGA and Pro Clima. But no matter how good the tapes, most important of all is how well they’re applied.

     

    Plan early and get advice from the experts

    “You really want to get your designing done early, get your planning done early and then don’t mess with it. Because every time you change it, there will be unforeseen consequences. Usually those will be things that make your airtightness worse or harder at least.”

    Paul encourages self builders to take advantage of the Passivhaus Open Days and talking to the people who have built them. There are also the AECB and UK Passivhaus conferences that people can attend and find out more about the network of experts.

    “There are networks of people and a lot of them are very committed people. They give their time, they give their energy and they often don’t charge as much as they should for it, because they believe in it.”

     

    Find out more

    Visit the website of Design Buro

     

    Transcript

    Download the transcript of the interview with Paul Jennings.

     

    Please connect with me

  • HPH225 : How to create a load-bearing straw bale Passivhaus home – with Andrew Goodman

    HPH225 : How to create a load-bearing straw bale Passivhaus home – with Andrew Goodman

    Architect Andrew Goodman explains what it took to create the UK’s first load-bearing straw bale Passivhaus home.

     

    Interview with Andrew Goodman

    Andrew Goodman is an architect with over 20 years experience running his own practice, currently as a sole practitioner based in Hertford. One of his recent projects has been for Dave and Mabel Howorth, who were looking to build a straw bale home for their retirement, with the added challenge of wanting to achieve the Passivhaus standard.

    Dave Howorth already had an interest in straw bale buildings and had previously participated on one of Straw Works‘ projects. He was convinced that it was a good way to build and was also attracted by the affordability it provided.

     

    The simple form suited both the straw bale construction and Passivhaus elements

    It took several years for Dave to find his plot of land. When he bought it, it already had planning permission for a chalet style bungalow, which wasn’t ever going to lend itself to either being built with straw bales or to the Passivhaus standard.

    The plot was in the curtilage of an old, listed dwelling with thatched roof and lime plastered walls, and the local vernacular for Dutch barn style curved roofs also gave the extra ceiling height they were looking for, so these both provided a starting point for evolving the design.

    Being a detached dwelling in an established orchard meant the trees would have some impact on shading the building in a positive way.

    Photos copyright of Agnese Sanvito

     

    The house needed to be suitable for their future requirements

    It was important to Dave and Mabel that the building should meet the Lifetime Home standard, which was about at that time (but since been partially absorbed into Building Standards). The standard had a dozen or so categories covering how someone with restricted mobility might approach and access the building, move through it with ease and move between levels if applicable.

    The brief was to provide three main bedrooms, living accommodation, separate kitchen, dining and living room. The Lifetime element was incorporated by providing an extra reception room on the ground floor with access to a wet room, which could be a bedroom with en-suite in the future if needed.

     

    A pre-application with the planners was largely positive

    The proposed building had roughly the same floor area as the original planning permission which was a help, and although the finishes were very different, they were judged to be appropriate for being in close proximity of the listed building, and planning permission was granted.

     

    The natural movement of straw may have an impact on airtightness over time

    The foundation is an insulated slab system. Then there is a taped connection between the slab and the internal wall finish, which crosses over the base plate detail that you need on any straw bale construction. Instead of building first floor joists into the walls, they used a ledger beam approach attached to the box beam, with a membrane between the ledger beam and the box beam that connects the two plaster layers, the ground floor and first floor.

    The curved roof uses a standard Intello membrane on the underside of the timber structure, which again is then connected to the render at first floor level.

    A previous attempt by Fran Bradshaw to build the first load-bearing Passivhaus straw bale house just missed out on achieving the standard. Hers used a structural timber frame, so the bales may not have been as compressed and loaded as those at Haven Cottage. Andrew’s assistant was convinced that load-bearing the straw bales would be the best way to go, and by using a wet lime plaster on the inside as the air barrier, it shouldn’t be any different than using it on a brick block cavity wall. Haven Cottage also has an external lime render.

    In terms of the construction, part of a ring beam is placed that can be used to compress the bales using wires that run from the base plate up to the top plate, which are then tightened. There is a typical compression of around 50mm for each storey height. Once it’s compressed it is loaded with the next level of construction up to the underside of the roof.

    Together with the structural engineer, they worked out a system of curved laminated beams that are actually within the overall depth of the roof. The roof has 40mm of Warmcel insulation. The laminated beams are only 300mm deep.

    “So, there’s a double joist system that minimises thermal bridges, loses the curved laminated beams – perhaps unfortunately, but it keeps the underside of the ceiling simpler and therefore the Intello membrane just runs in a very, very simple way.”

    Airtightness tapes were used to connect the windows to the wet plaster reveals, and time will tell whether the added movement that straw bales naturally have will cause cracks in the render and impact on the airtightness. Andrew recommends taking care to look at the building over time, checking the plaster and renders and making sure they are kept in good condition to ensure there is no moisture ingress.

     

    The straw bale construction process provided an education for others

    Dave was able to take a 12 month sabbatical from work and project manage the construction. He used a specialist substructure and groundworker who did the slab and drains and anything else below the ground. There were a couple of carpenters who worked collaboratively throughout on all of the timber elements. Straw Works provided teams of people to build the walls in their usual method, providing training to people who were interested in learning about the skills of straw bale construction. There was also a specialist roofing contractor.

    Dave did all the airtightness taping and installation of the MVHR system himself.

     

    Solar PVs provide the majority of hot water

    The original design and PHPP model for the building was using a gas-fired boiler for heating, but Dave decided, partly for cost-saving, not to install the gas main.

    “There’s a duct into the building which a gas main could be fitted into in the future, should someone want to do that, but fortunately with the introduction of PHPP 9, the primary energy renewables option enabled it to be certified. Without that, it wouldn’t have been certifiable because it’s electric-only heating.”

    There are three heaters in the house in the hallway and bathrooms, and a post-heater in the MVHR which raises the temperature a little bit above whatever it has come through the heat exchanger with.

    Haven Cottage has solar PVs which provide all the required hot water in the summer, with a bit of Grid electricity needed in the winter to top it up. Passivhaus Plus Magazine has calculated that the building is actually making a profit on the electricity side.

     

    Lack of straw bale experience was no obstacle

    Andrew didn’t have any experience of straw bale buildings before coming into this project, but wasn’t daunted as he found sufficient information around to understand the normal procedure, and from that work out how to do things slightly differently to meet the needs of achieving the Passivhaus standard.

    “I would love to build more straw bale buildings. I’m not convinced it’s a solution to our mass housing needs but there is definitely a place for it, especially within the self-build world, because of that collaborative nature of the process itself.”

     

    Find out more

    Visit the website of Good Architecture

     

    Transcript

    Download a transcript of the interview with Andrew Goodman.

     

    Please connect with me