  • HPH150 : Where is the balance between renewables and a fabric first approach? – with Alex Baines

    HPH150 : Where is the balance between renewables and a fabric first approach? – with Alex Baines

    Despite his background in renewables, Alex Baines explains why he embraced a fabric first approach on his self build project.

    Alex Baines in his office

     

    Interview with Alex Baines

    We’ve been following the progress of Alex Baines’ Long Barrow Passivhaus self build in episodes 74 and 100. This time we’ve brought him back to the podcast to draw on his background working in renewable energy. He first became interested in the idea back in 2008 and went on to do a Masters in Renewable Energy at the Centre for Alternative Technology, before getting a job advising a mechanical and engineering company about renewables installations.

     

    Renewables were heavily incentivised to encourage meeting carbon emissions reduction targets

    Until fairly recently it seemed to many that renewables were being hailed as the solution, and the industry was heavily incentivised with feed-in tariffs and the Renewable Heat Incentive to encourage take-up. The successful promotion of the industry meant there was, and still remains, a perception that by using renewables you create a ‘green’ or ‘eco’ house.

    It wasn’t long before Alex came to the conclusion that while renewables were a great part of the solution, they should only be the final part of the solution: “because technically you can get to zero carbon by building a pretty bad building and whacking in a massive amount of renewables.”

     

    Renewables should be “the final part to get you to the bit that you can’t avoid”

    For Alex it became important to look at fabric first in the initial instance, and then consider renewables for the parts that can’t be avoided, such as electricity. Whereas with Passivhaus you can avoid the need for the majority of heating, you can’t avoid the need for electricity around the house, which is where renewables can still play their part.

     

    Reducing the energy demand of a building means fewer renewables are needed

    It was quickly apparent to Alex that Passivhaus was where his focus needed to go, because he cared about reducing the energy demand in the first instance.

    “So you look at a building, the building is the demand and the renewables are something that meets that demand. So if you can reduce the demand then you reduce the size of your generator.”

    Alex points out that renewables will eventually fail, and at that point the building will no longer for example be zero carbon, or running at an improved efficiency.

     

    A change in public perception may need to be driven by government

    Alex explains that if/when the Building Regulations become more stringent, then people’s understanding may change too, as currently there is a general lack of knowledge and promotion around it. He uses the example of Brussels – where Passivhaus standard has been adopted – which has resulted in manufacturers coming to the city because that’s where the demand is (rather than sourcing products from overseas).

     

    Passivhaus is really a ‘human comfort’ standard

    According to Alex, the current Building Regulations don’t focus on a holistic approach of what is best for the occupants. Instead they are made of separate parts looking at individual elements, for example, ventilation requirements having no link to acoustic requirements, and having no link to energy demands.

    “I would much rather we just said right, let’s go for a human element design and actually funnily enough, you focus on the human element you end up with Passivhaus because that’s where Passivhaus came from.”

     

    Long Barrow Passivhaus progress – know when you can take a pause!

    Alex had opted not to take a mortgage for his self build until they got to the airtight / watertight shell stage, so when his employment situation changed nearly a year ago, they decided to pause the project. Because they are using Insulated Concrete Formwork (ICF) as a construction method they were able to pause before getting the windows in and the waterproofing on. With other building methodologies it wouldn’t be possible to pause until they are airtight and watertight, but Alex suggests you work out at what stages you would be able to take a break if circumstances unexpectedly arose that might make it necessary.

    Work is due to recommence shortly with the insulation waterproofing going on the roof, before putting the windows in and waterproofing the rest of the building. Once the services have been connected up Alex can start on the internal layout. The internal space has been designed to be flexible, which has the benefit that Alex can work on one part while still being able to live in the other spaces. If the budget allows at the end, he will be installing photovoltaics for generating electricity and solar thermal panels to provide the hot water.

    Roof-on-Long-Barrow

     

    Find out more

    Follow Alex Baines on Twitter

     

    Transcript

    Download a transcript of the interview with Alex Baines.

     

    The Hub update

    We’re just getting ready for our next progress call, where we bring people together within the community and try and resolve any issues. It’s always interesting to see the hurdles that people are facing at the various stages of their projects.

    Our new module is about VAT refunds, explaining how the process works and what you can and can’t claim for.

    The new module also ties in with the latest video project we’re following – Buckinghamshire Passivhaus – which started out as a renovation project. After doing all their research they realised it just didn’t make sense – either financially or in terms of risk and complexity. Combined with various other reasons they decided to opt for a new build instead. If you’re a Hub member you can check out the video now, and we have the next instalment coming very soon.

     

    Please connect with me

  • HPH023 : A Cottage Built with Structural Insulated Panels (SIPs) – with Kingsley Barraclough (Client Case Study)

    HPH023 : A Cottage Built with Structural Insulated Panels (SIPs) – with Kingsley Barraclough (Client Case Study)

    Kingsley Barraclough shares his experience of building a house and explains why he decided to use structural insulated panels (SIPs).

    Kingsley-profile

     

    Interview with Kingsley Barraclough

    Kingsley’s background as a plumber has given him plenty of opportunities to see houses losing heat and that’s why he was determined to build himself an energy efficient home. So, his goal was to create a small, flexible space with lots of natural light, that was easy to run and also cheap to heat. The new cottage would have a floor area of 125m2 and be built on a plot beside his existing property.

    Kingsley-plot-2

     

    Despite Construction Experience, Kingsley Chose to be Just the Client!

    Although Kingsley’s an experienced plumber he did not do any of the work himself, reasoning that it would not be a good idea to change the dynamic of a team that already works well together. He also hired a project manager because he believed that while he can work in a team, he did not have the necessary skills required to run a team and deal with the many things that can go wrong!

     

    Hiring a Contract Administrator Made Dealings Simple

    Kingsley took the advice of his project manager and hired a contract administrator. This effective third party acts as a membrane between client and builder, and provides some neutral ground should any problems arise. Kingsley says that it worked well for both parties.

     

    Initially Kingsley Discussed The Outcomes He Wanted to Achieve with His Architect

    Kingsley’s first step was to sit down with an architect and talk through what he wanted to achieve from the new house. Whereas his existing home was from 1884 and had lots of nooks and small rooms, in contrast he was keen to create a more contiguous living space.

    Kingsley-cement-floor

     

    The SIPs are Engineered to Suit the Design

    Once a design was created and planning permission acquired, Kingsley had to decide on a build method. After researching structural insulated panels as an option and visiting houses that had been built with them, he chose this route. An engineer then reworked the SIPs method of construction to fit with the design. For example, where the timber panels were not suitable the engineer reinforced it with steel construction to achieve the required look. At no point did Kingsley have to compromise with the SIPs.

     

    A Structural Insulated Panel is Like a Sandwich!

    Kingsley talks about the structural insulated panels he used which consist of 2 layers of OSB with a core of PIR foam. [An additional 25mm insulation, TW55, was also added to these Kingspan Tek panels on the inside behind the plasterboard lining, which proved very cost effective.] Once machined these panels form part of a kit, which turns up labelled and numbered. There are rebates, grooves and fillers that lock all the panels together.

    Kingsley-SIPs-close-up

     

    SIPs are Incredibly Quick to Put Up

    With the hard work done in a factory, one key advantage of SIPs is that they can be assembled on site very quickly. In this case, the ground floor was done in the first week and the second floor was done in the second week.

     

    The Precision of SIPs is Greater Than a Conventional Build

    Having been in the trade for many years, Kingsley says the nature of block and breeze construction means you tend to work to the nearest inch. However, with SIPs you are working to about 3mm.

     

    SIPs Allow You to Work on Two Faces at Once

    Once the timber cell has been put up the services can be going on inside – pipework, electrics, etc. – while brick work or cladding can be underway on the exterior. Wet trades are not crossing paths with the services.

    Kingsley-SIPs-begin

     

    Kingsley Presented His Intentions to His Neighbours

    Kingsley wanted his house to be a comfy fit for everyone in the area and so he negotiated with the people either side about the aspect, size of the building, etc. As someone who really values his neighbours, presenting his intentions at every stage of the project worked very well.

    Kingsley-building-up

     

    The Cladding Needs No Maintenance

    Two thirds of the face work is in a cottage mix of bricks (three local bricks that are used randomly) and then one third has got a modern version of weatherboard, which is a concrete board, called Eternit board (made by Marley). It gives the impression of being wood but is good for minimising heat losses and also will never need to be painted.

     

    The SIPs Hold up the Bricks!

    Kingsley points out that the brickwork – the face work – is attached to the SIPs with brick ties in the conventional way, so it’s not just held there by gravity. It is secured in the same way that brick to breeze block is secured, but really the SIPs panels hold up the bricks, not the other way around.

    Kingsley-finished-exterior-1

     

    Buying Windows From Abroad was Cheaper

    Kingsley put a lot of effort into finding window frames. The triple-glazed ones he eventually bought were dramatically less than getting them locally. Kingsley does not understand why this is.

     

    Put Your Money into the Fabric of the Building

    After considering many options including Huf Haus, but trying to temper budgets and reality, Kingsley ended up concluding that the money is better spent making sure you don’t need energy than in having very fancy low cost energy. So he put a lot of effort and money into making sure he doesn’t lose heat in the first place (rather than having a cheap source of it).

     

    Minimise Your Dependence on Technology

    Kingsley did not invest in heat pumps or other renewables because he thought they were too expensive and he didn’t want to have the worry of maintaining them as he got older. The thought of claiming on warranties of companies in 10 years for £30,000 bits of kit somewhere in the ground was something he wanted to avoid.

     

    The House is a Hermetically Sealed Box

    Although the appearance may be conventional, the house is airtight and very well insulated. It uses an air management system (mechanical ventilation with heat recovery) to bring in new atomised air but without the heat losses. 80% of the heat of the expelled air is saved and there is a full air change in the house every hour and a half.

    Kingsley-interior-1

     

    Installing Cabling for PV Means it Could be Easily Added Later

    A modern high efficiency condensing gas boiler drives the underfloor heating and the hot water, etc. Plus there is a cylinder that will accept solar and cabling to allow for PV at a later stage. Kingsley has no plans to install renewable technology but if efficiencies continue to improve, he wants to make sure he can add them retrospectively (without having to change cylinders and knock holes in the walls to add wires, etc.).

     

    Coordinating the Utilities Proved Difficult

    Although Kingsley could get the gas and water companies to be pretty cooperative, he really struggled with UK Power Networks. Kingsley’s advice, for anybody doing a new build in the UK, would be to get that bit applied for at the same time as you get your planning permission. There is a 90 days notice period, even from when they say yes! And this does not necessarily mean they arrive on the 91st day. So, organising this is a priority because not having electricity reliably is going to be a problem. Kingsley says having a contract administrator really helped.

     

    Life is Much Easier When All The Contractors Want the Same Outcome

    Kingsley believes he was very fortunate to have a team that shared his vision and all clicked together. He gives the example how if his interior designer came up with a good idea for the kitchen, the person building the kitchen would readily help to achieve it. There were no hidden agendas.

     

    Having Builders Who Got on With the Neighbours Helped

    Kingsley was very pleased with his team and thought it was fantastic to have builders that put themselves out to get on with his neighbours. He says this set the flavour for the build and eased pressure points with parking, etc.

    Kingsley-finished-exterior-2House designed by Martin Roberts from Cubed Projects

    Transcript

    Download a transcript of the interview with Kingsley Barraclough.

     

    Ask Your Questions or Share Your Feedback

     

    Elrond Burrell on Home Style Green

    Elrond Burrell is a guest on the Home Style Green podcast. He gave a really good explanation of the Passivhaus standard (the comfort standard). Check out episode 30: Is Passivhaus relevant to New Zealand?

    Home-Style-Green-logo

     